Updated August 23, 2024:
This project was completed in August 2024. Construction started in March 2024.
For more information about this CDOT project, visit CDOT’s webpage.
Completed
Updated August 23, 2024:
This project was completed in August 2024. Construction started in March 2024.
For more information about this CDOT project, visit CDOT’s webpage.
The following update was provided by CDOT in March of 2024:
As of mid-September 2022, the project moved in a different direction. The Colorado Department of Transportation (CDOT), rather than Douglas County, will plan, build and maintain the new signal.
CDOT determined that Douglas County’s concept / idea of installing temporary traffic signal poles that use span wire to be unacceptable since CDOT considers the County’s approach / idea to be appropriate only as a short-term solution (for up to 4 years of service).
CDOT does not have construction funding currently identified in its 10-year plan to complete the widening and reconstruction of US 85 between Sedalia (State Hwy 67) and Castle Rock Parkway. This lack of funding influenced the type of traffic signal poles and other traffic signal elements that CDOT would allow to be used at the US 85 / Daniels Park Road intersection, and therefore this proposed type of traffic signal infrastructure will need to be left in-service much longer than the parties originally anticipated.
Josh Breedlove is the CDOT Resident Engineer, and he will manage the project as it moves forward in a slightly new direction. Josh can be reached at Joshua.Breedlove@state.co.us
Background Information:
The County believes this project to be a very important safety improvement and is still planning to provide CDOT with a significant financial contribution (equal to what the County currently appropriated for the temporary traffic signals that would have utilized span wire) in a future Intergovernmental Agreement (IGA).