01.

Help Me With...

Select from list
My Residential Property
My Driver's License or Vehicle Registration
Requesting Assistance
Elections
Health Department

02.

Select from list
My Property Valuation
Understanding My Valuation
Paying My Property Tax
Neighborhood Sales
Building Permits
Vehicle Registration - New Stickers
Vehicle Registration - New Vehicle
Drivers License - New or Renew
New Resident Vehicle Registration
Adult Protection
Child Welfare
Child Support
Child Care
Financial Assistance
Medical Assistance
Food Assistance
Register to Vote / Update Voter Registration
Upcoming Election Information
Ballot Drop Box Locations
Voter Service and Polling Centers
Birth/Death Records
Restaurant Inspections
Community Health
Child Care Center Inspections
Septic System Inspections
Emergency Preparedness & Response
Disease Surveillance
Mental and Behavioral Health Education
Community Health and Clinical Services
Women, Infants and Children

03.

×
× Close

News

I-25 South Gap project spreads holiday cheer with the gift of progress in 2020

Information provided by the Colorado Department of Transportation

Posted on December 21, 2020 2020Transportation

Share

Three more structures – an interchange and two wildlife crossings – will be completed in December as part of the Colorado Department of Transportation’s I-25 South Gap project with general contractor Kraemer North America to improve safety and travel reliability along Interstate 25 between Castle Rock and Monument.

The Greenland Road and I-25 interchange is expected to open the morning of Dec. 22. Since June 2019, crews have been working to transform this single-lane box culvert (circa 1948) into a full two-lane underpass while also flattening curves along I-25 approaching the interchange and widening the interstate. With the bridge complete, traffic will be shifted into its final alignment on I-25.

Additionally, two new wildlife underpasses are complete. One is located just south of the Greenland Road interchange, and the other is just north of the County Line Road bridge. Each wildlife underpass is 100 feet wide and 18 feet tall. A total of four new underpasses along this wildlife corridor are expected to result in a 90% decline in wildlife versus vehicle collisions.

TRAVEL IMPACTS

For traffic to be shifted into its final alignment near Greenland Road on Dec. 22, crews will require two separate impacts:

Finalizing the new I-25 alignment and the interchange will require striping. Painting is highly dependent on both moisture and temperatures, so this schedule could change. Please visit i25gap.codot.gov for updated information.

While a majority of major impacts will be complete in this area following the traffic shift, motorists should continue to watch for crews and lane closures as they complete work on mainline I-25. Flaggers will still be present at the Greenland Road interchange, so please practice extra caution in the area.

STAY INFORMED
Project hotline: 720-745-5434
Web: i25gap.codot.gov

Your County. Your News. Get it first.

Be among the first to receive news as it happens. Subscribe to our online news push, and select your specific news focus and delivery preferences. Visit the Live Town Hall page and register for Town Hall notifications to ensure you are contacted to participate in future community conversations about topics important to you. Both services are free, and you can unsubscribe at any time. And don’t forget to follow Douglas County on Nextdoor, Facebook, Twitter, Instagram, LinkedIn and YouTube.