Project timelines have changed – please see “Schedule” section below for more information.
Planning/Design
Updated August 15, 2024
Project timelines have changed – please see “Schedule” section below for more information.
Proposed improvements:
The proposed improvements will improve the safety, traffic operations and reduce congestion. The design plans are about 90 percent complete. IREA/CORE began relocating major utilities along Pine Drive, as well as relocating their existing facilities along Pine Lane, which conflicted with the proposed improvements. IREA/CORE’s construction schedule must be delayed to provide them with adequate time to obtain several permanent easements.