01.

Help Me With...

Select from list
My Residential Property
My Driver's License or Vehicle Registration
Requesting Assistance
Elections
Health Department

02.

Select from list
My Property Valuation
Understanding My Valuation
Paying My Property Tax
Neighborhood Sales
Building Permits
Vehicle Registration - New Stickers
Vehicle Registration - New Vehicle
Drivers License - New or Renew
New Resident Vehicle Registration
Adult Protection
Child Welfare
Child Support
Child Care
Financial Assistance
Medical Assistance
Food Assistance
Register to Vote / Update Voter Registration
Upcoming Election Information
Ballot Drop Box Locations
Voter Service and Polling Centers
Birth Certificates
Community Health
Death Certificates
Environmental Health
Household Waste Management
Public Health Services

03.

×
× Close
Public Works

US 85 / Titan Interchange Improvements

Roadway

Budget

Contract for $984,521.49

Project Manager

Brolin Bundy
[email protected]

303-660-7490

Contractor

Kraemer North America - Justin Leuenberger
[email protected]

mobile 303-594-6262 | office 303-688-7500

Project Update

October 17 – 24, 2022: The contractor will be adjusting a signal head and programming the controller, and seeding and mulching of the slopes and disturbed areas.

October 18, 2022 – Night Work will begin at 7 p.m. to restripe Titan Parkway and stripe the widened on ramp.

Description

See “US 85 and Titan Interchange Improvements” Map Location in pictures below.

This Project consists of widening the US 85 northbound on-ramp at Titan Parkway to improve safety and traffic operations. The Project also includes striping modifications on Titan Parkway to add a second left turn lane and widening of the northbound on-ramp which includes: guardrail, concrete slope and ditch paving, soil retention mat, and curb and gutter.

Signing and Striping Plan for US 85 / Titan Interchange

Prior to construction, Douglas County worked with CDOT to get final environmental approval and other CDOT access permits to allow the County to widen the northbound US 85 on-ramp and restripe Titan Road over US 85. Douglas County’s consultant also performed a subsurface utility engineering investigation and determined which major utility companies needed to relocate their facilities before construction of widening the northbound ramp could occur.

The Board of County Commissioners approved a construction contract with Kraemer North America on July 26, 2022 for this project from Titan Parkway to northbound US Highway 85. This project will improve safety and traffic operations for the on-ramp, which is located near the Roxborough and Sterling Ranch subdivisions.

Schedule

Construction started on August 18, 2022, and is expected to be substantially completed before the end of the year (2022).

Project Manager
Brolin Bundy, P.E.
[email protected]
303-660-7490