October 17 – 21, 2022:
Bannock Drive
- Completion of base course installation
- Completion of curb and gutter paving
- Asphalt roadway paving
Poncho Road
- Continuation of storm line and structures installation
- Completion of sanitary sewer main tie-in into the existing main
- Continuation of conduit/sleeving installation for dry utilities
- Water services installation for lots
October 24 – 28, 2022:
Bannock Drive
- Completion of asphalt paving
- Final erosion control devices installation and repair
- Installation of roadway signage and marker posts
- Demobilization of the site and site clean-up
Poncho Road
- Completion of the water services installation to the lots
- Sanitary sewer main tie-in to the existing Kenosha Dr manhole*
- Begin sub-grade prep for base course installation
*During the sanitary sewer main installation into the existing Kenosha Dr manhole, the contractor will be required to close a segment of Kenosha Dr to through traffic due to the deep depth of the excavation during the day. The road will be reopened at the end of each day. This work is expected to take two (2) days to complete. During this time, all residents within the segment closure will be able to access their property/driveways. The contractor will maintain the ability for emergency vehicles to pass through at any time during the work.