Sidewalk Repairs – Completed
Rotomilling – Completed
Asphalt Paving – Completed
Roadway
Sidewalk Repairs – Completed
Rotomilling – Completed
Asphalt Paving – Completed
The 2022 neighborhood street paving program in Douglas County includes streets in the Dove Ridge/Cottonwood area. See the 2022 Neighborhood Street Paving Map for specific locations.
On each street, work will be completed in phases – the first phase consists of sidewalk repairs and curb ramp upgrades, which will be performed by the County’s sidewalk repair contractor Chato’s Concrete. Sidewalk repairs will begin after March 15 and will usually take between 2 and 4 weeks per neighborhood; work on a single block will generally take 3 to 4 days.
The second phase will take place later in the summer and consists of rotomilling to remove some of the top layer of asphalt, which generally takes 2 to 4 hours or less per block to complete, and will be performed by the County’s asphalt overlay contractor, Martin Marietta Materials. The final phase follows rotomilling by 1 to 2 weeks and includes placing the new overlay; this last phase may take 4 – 8 hours to complete.
During construction, access to driveways will be available, with occasional short delays. If the sidewalk contractor needs to replace the walk in front of your driveway, they will notify you so you can move your vehicles before the work is done.
One to two weeks before the start of sidewalk repairs, the County will send Cone Zone Mailers to notify adjacent residents of the planned work. Cone Zone Mailers will also be sent 1 to 2 weeks before the start of rotomilling.
One to two days before the start of each phase of work, the Contractor will deliver a Cone Zone door hanger with the date of the start of that phase of work on your block.
Two days before the start of rotomilling and paving, no-parking signs will be posted along the streets scheduled for work. Construction will be done Monday through Friday between 7 a.m. – 7 p.m.
Phone: will be updated soon
NOTE: If your vehicle was towed because it was left in the construction zone, please contact Westside Towing at 303-688-5244 for information on where your car was towed.
See “Project Update” section above.