Phase 1 Schedule – Legend High School to Alpine Drive
- 2020 – Engineering staff advanced surveying, design, subsurface utility engineering and initiated some critical ROW acquisitions.
- 2021 – advance final design, continue ROW acquisition and coordinate proposed utility relocations.
- 2022 – complete final design, ROW acquisition and utility relocations will continue.
- 2023-2024 – Construction is anticipated to begin in late 2023 or early 2024 (pending funding); and the project will take 18 to 24 months to construct.
Phase 2 Schedule – Alpine Drive on Hilltop Road to Flintwood Road on Singing Hills Road
- 2020 – Engineering staff advanced surveying, design, and subsurface utility engineering.
- 2021-2022 – advance design to 60% level to identify ROW needs and utility relocations.
- 2023 – 2024 – Complete final design of the project, ROW acquisition and utility relocations will be completed in advance of construction.
- 2025-2026 – Construction is anticipated to begin in early 2025 (pending funding); and the project will take 12 to 18 months to construct.