The 2023 neighborhood street paving program in Highlands Ranch includes streets in the Wagon Box Circle, Jaguar Way, Huntington Circle, Cheetah Tail, and South Ranch Road areas.
On each street, work will be done in three phases:
- The first phase consists of sidewalk repairs and curb ramp upgrades. Sidewalk repairs will begin after April 3, 2023, and will usually take between 2 to 4 weeks to complete per neighborhood; while work on a single block will generally take 3 to 4 days. Estimated completion date: April 24, 2023.
- The second phase will take place later in the summer and consists of rotomilling to remove some of the top layers of asphalt, which generally takes 2 to 4 hours or less per block to complete.
- The third (and final) phase follows rotomilling by 1 to 2 weeks and includes placing the new overlay; this phase may take 4 – 8 hours to complete.
During construction, access to driveways is allowed, with occasional short delays. If the sidewalk contractor needs to replace the sidewalk in front of your driveway/address, they will notify you directly so you can move your vehicles before the work is done.
Additionally, to notify adjacent residents of the planned work, Douglas County will send out Cone Zone Mailers 1 to 2 weeks before the start of sidewalk repairs and/or rotomilling work.
A minimum of 2 days before the start of rotomilling and paving (overlay), no-parking signs will be posted along the streets scheduled for work.
Construction will occur Monday through Friday between 7 a.m. – 7 p.m.
Sidewalk Contractor:
Chato’s Concrete, LLC
Asphalt Pavement Contractor:
Martin Marietta Materials, Inc.
NOTE: If your vehicle was towed because it was left in the construction zone, please contact Westside Towing at 303-688-5244 for information on where your car was towed.