May 25, 2022
The new design alternative must:
- Be compatible with Arapahoe County’s Inverness Drive West Bike and Pedestrian Facilities Project which is located immediately to the north of our project limits
- Minimize construction impacts as well as utility relocations; and requires installing new traffic signals at the existing closely spaced intersections.
- Project limits will likely be expanded to include a mill and overlay of the existing pavement on County Line Road between the southbound I-25 off-ramp and the South Valley Highway / Inverness Way South / Inverness Parkway Intersection.
- Improve traffic operations and cost closer to $5 million.
To advance construction in 2024, in 2022/2023, the parties will need to agree on a revised plan, finalize a stakeholder funding plan, prepare revised construction documents, acquire additional right-of-way, and relocate impacted utilities.